Voltage optimiser cuts electricity bills by 17.3%

An immediate 17.3% reduction in electricity consumption has been achieved following the installation of a voltage optimiser at Peasley Cross Hospital in St Helens. Before the installation of the equipment from Streamline Power, the average voltage on site was 246.3 V, peaking at 252.8 V —close to the legal maximum of 253 V. The voltage optimiser has reduced the voltage to 223 V, balanced the incoming phases and controlled the incoming voltage to within 0.5% of target.

The project will pay for itself in 32 months and deliver an internal rate of return of 39%.

Installation took two working days, and the electricity supply was switched over during a period of low demand in the working day.

For more information on this story, click here: December 2011, 81
Related links:
Related articles:



modbs tv logo

New Sustainability Director for Wates Group

Wates Group, a family-owned development, building and property maintenance company, has appointed Cressida Curtis as its new Group Sustainability Director.

Domus Ventilation appoints new contractor sales managers

Ventilation systems manufacturer Domus Ventilation has announced the arrival of three new Contractor Sales Managers.