This massive collection of flexible ductwork helped kept the data centre of a major tele-communications company operating when a burst pipe threatened loss of critical temperature control. Andrews Chiller Hire was called into to deliver a solution that would achieve and maintain constant air temperature while the in-house air-conditioning system was shut down for repair and test.

The water leak was discovered on a Saturday morning, and the emergency call to Andrews Chiller Hire was made on the same afternoon. Within an hour, a solution had been formalised with the customer and the required equipment and engineering team mobilised.

To meet the demands of this tele-communications datacentre, which is split over two floors, Andrews supplied a range of duplicated equipment to be installed on opposite sides of the building.

On each side of the building a 750 kW chiller delivered chilled water to five air handling units which delivered chilled ambient to the building, three supplying the top floor and two the lower-ground floor. There was also a 550 kVA generator on each side of the building connected to a 3000 l fuel tank.

For more information on this story, click here: July 2015, 128
Related links:
Related articles:



modbs tv logo

New Sustainability Director for Wates Group

Wates Group, a family-owned development, building and property maintenance company, has appointed Cressida Curtis as its new Group Sustainability Director.

Domus Ventilation appoints new contractor sales managers

Ventilation systems manufacturer Domus Ventilation has announced the arrival of three new Contractor Sales Managers.