Preventing boiler dry cycling at the King’s Cross Hospital in Dundee has achieved average fuel savings of 7% with a payback of 1.8 years. Sabien Technology verified the savings for its M2G boiler-load optimisation controls for NHS Tayside.

Delivering cost savings is a key area of focus for NHS Tayside,’ explains its energy co-ordinator John Ruddy. ‘We decided to verify what savings M2G could deliver, and we are pleased with the outcome.’

Installation work has no impact on clinical practice, enabling all areas of the hospital to function as usual.

The measurement and verification project involved M2G units being installed on Hamworthy Wessex 200HE, Hoval Ultragas 500 and Hamworthy Purewell Classic boilers. Sabien’s M1G was also installed on the hospital’s direct-fired water heaters. Energy consumption was compared to previous consumption, using degree-day data to allow for weather variation.

For more information on this story, click here: January 2016, 80

comments powered by Disqus

Search

Welcome

Welcome to Modern Building Services Online, the web edition of Modern Building Services (MBS) journal and the UK's most popular Building Services engineering site. Modern Building Services covers the entire Building Services Engineering industry. This site contains archived content from the journal, plus web-specific content.

When you go to our digital edition, you can also access the archive of digital editions.
June 2017: DIGITAL EDITION
ARCHIVE OF DIGITAL EDITIONS

Modern Building services has a group
on Linkedin - join us!

Construction Week

Jobs

  • Lead Mechanical & Electrical Engineer

     Do you want to make a real difference? A unique opportunity has arisen for an established Lead Mechanical and Electrical Engineer to work in the Buildings and Construction group, the in house multidisciplinary design practice at Dorset County Council .........

more jobs »

Poll

"Is the Building Services industry lagging behind in the implementation of BIM?"



Calendar