Andrews will keep data centre operational during refurbishment

Published:  06 July, 2016

Andrews Chiller Hire, chiller

Andrews Chiller Hire will maintain cooling capability for a telecommunications provider by supplying 1.4 MW of cooling while the in-house chillers are taken off line during a major refurbishment programme. The two chillers will run in series for direct connection to the existing flow and return connections.

Andrews will also supply power-generation equipment to establish a totally stand-alone system, ensuring adequate and essential cooling to critical operational suites housing advanced computerised technology.

The space available at the site meant that the chillers need to be placed end to end, with cable ramping used to run to the generators.

For more information on this story, click here: July 2016, 83

comments powered by Disqus

Search

Welcome

Welcome to Modern Building Services Online, the web edition of Modern Building Services (MBS) journal and the UK's most popular Building Services engineering site. Modern Building Services covers the entire Building Services Engineering industry. This site contains archived content from the journal, plus web-specific content.

When you go to our digital edition, you can also access the archive of digital editions.
July 2017: DIGITAL EDITION
ARCHIVE OF DIGITAL EDITIONS

Modern Building services has a group
on Linkedin - join us!

Construction Week

Show

Jobs

  • Property Surveyor

    Property Surveyor/ Building Service Surveyor needed to work within the Technical Services team for the management of water hygiene/ legionella risk within DCC's property portfolio. We are looking for an experienced and dynamic team member to join our T......

more jobs »

Poll

"Is the Building Services industry lagging behind in the implementation of BIM?"



Calendar