YorPower complete standby-power installation in double-quick time

YorPower, standby power

Part of two 1800 kVA MTU diesel generators, each weighing 14 t, is craned onto the roof, 15 storeys up, of an office development in Manchester for a contracted awarded to YorPower to provide N+1 backup for an American bank. The task was carried out by a 200 t crane with a reach of 30 m while a road was closed from a Friday afternoon to Monday morning.

Ian Thompson, managing director of YorPower, told us, ‘The whole project from order through procurement of major components, assembly, build, completion on site, including installation and commissioning, took just 18 weeks. Typically a project of this nature would take 30 weeks from start to completion on site.’

Related links:
Related articles:



modbs tv logo

Heat network confidence outpaces progress in social housing

Baxi surveyed 100 housing associations and 102 local authorities and councils responsible for managing or operating heat networks this summer, alongside in-depth interviews with five housing associations, a heat network consultant and heat network contractor.

Signify showcases F1 lighting partnership at Brackley campus

MBS Features Editor Russell Drury was among a group of journalists from across Europe invited to visit the Mercedes-AMG PETRONAS Formula One Team’s headquarters in Brackley, where Signify showcased its partnership with the team and the shared focus on innovation and sustainability.