Shenton supplies generator to meet peak loads at a factory

Shenton, standby power, generator
This ‘standby’ generator from Shenton Group eliminated the need for a costly substation at a factory to meet higher peak loads.

Faced with a potential bill in excess of £50 000 for an onsite electrical substation to meet greater demand from increasing production time from 12 to 24 h a day, Herrco Cosmetics approached Shenton Group to provide a bespoke generator to automatically manage peak loads. The bespoke generator for the factory at Halesworth, Suffolk, has an output of 138 kVA and a specially built control panel.

The generator is housed outside in a super-silent acoustic and weatherproof canopy on a concrete plinth. Shenton’s total solutions package included installation, testing and commissioning, and a regular maintenance programme and ongoing fuel-delivery service.

Shenton Group installed equipment to measure peak-load requirements before creating a tailor-made solution.

The generator synchronises with the mains, enabling it to monitor the factory’s power consumption and provide additional power during times of peak load. It can also provide standby during mains failures.

For more information on this story, click here: October 2011, 128
Related links:
Related articles:



modbs tv logo

Lighting the way

Halesowen College has set a sustainability example for higher education institutions by installing smart lighting as part of its latest environmental initiative, making up to 85% energy savings compared to the previous system.

BESA updates HIU Test Standard

The Building Engineering Services Association (BESA) has announced an important update to its UK Heat Interface Unit (HIU) Test Standard, further strengthening performance benchmarks and supporting the sector’s readiness for incoming heat network regulation.