An education in prefabrication

pipe, pipework, Pipe Center, prefabrication
Pipe Center has supplied 288 prefabricated modules for the new sixth-form building of Newcastle College.

Prefabricated pipework is a design feature of Newcastle College’s new sixth-form building. Pipe Center worked with Vaughan Engineering Group to design and develop 288 modules which will contain the building’s main services. These modules comprise electrical containments, heating, chilled water and domestic services.

Pipe Center and Vaughan Engineering Group worked to a tight 6-week timescale from initial order to the first batch arriving on site.

‘We’re working to strict deadlines,’ explains Andy Mcleod, project manager at Vaughan Engineering. ‘The nature of the site also meant we had to work with our client to ensure deliveries were carefully timed and controlled. Using Pipe Center’s modular-engineering facility has saved us a considerable amount of time.’

For more information on this story, click here: September 2012, 80
Related links:
Related articles:



modbs tv logo

Baxi survey reveals care home leaders need support to achieve heat decarbonisation goals

Baxi recently surveyed over 400 senior and middle management care home managers in both the private and public sector this summer in an effort to understand the enablers required to help decarbonise the sector.

CIBSE launches Society of Vertical Transportation to elevate standards worldwide

CIBSE has officially launched the Society of Vertical Transportation (SoVT), an international professional community for individuals and organisations working across the design, engineering, installation and innovation of lifts, escalators and emerging vertical mobility systems.