RHI payments will cover cost of biomass installation in five years

Industrial GRP, a manufacturer of glass-reinforced plastic products expects to recover the initial costs of its new biomass boiler heating system in just five years from RHI payments alone. There will also be a significant reduction in fuel costs. The system was installed by Thermal Earth and can provide 186 kW of heat for the warehouse and offices.

The initial cost of the system was £110 000, and the RHI payments are expected to be £21 000 a year for 20 years.

Three Poncast KP63 wood-pellet boilers are installed in cascade, enabling one boiler to be serviced or repaired while the others continue running. Controls enable up to five heating circuits, including DHW, accumulator tanks and solar system to be run from one device.

A new radiator system along with fan-coil units into the warehouse was installed to enhance the efficiency of the new system.

For more information on this story, click here: September 2014, 84
Related links:
Related articles:



modbs tv logo

Commercial landlords face MEES compliance crunch

Two-thirds of UK commercial real estate (CRE) owners admit they are “not fully compliant” with energy efficiency regulations, according to new research from smart buildings specialist LMG. 

Recognising outstanding achievements at CIBSE Building Performance Awards 2025

The Park Plaza Westminster Bridge in London came alive on 27th February 2025 for the prestigious CIBSE Building Performance Awards.