G&H installs biomass boiler

A biomass boiler has been installed at Harrogate Grammar School as part of a project to modernise its heating and hot-water systems. The project involved G&H Sustainability completely stripping out the existing plant room and stripping out old gas-fired boilers , water heaters, pumps and pipework.

The old equipment was replaced with a fully automated 199 kW biomass boiler from Hoval and a building-management system for complete control.

Andrew Hudson, a director of G&H Sustainability, said, ‘We prefabricated the majority of the pipework within the plant room due to the time constraints of the project. This worked well because we were able to complete the on-site installation works in a much shorter time frame’

For more information on this story, click here: April 2015, 104
Related links:
Related articles:



modbs tv logo

The electric economy

Universities drive down carbon emissions

Kevin Pocock of Mitsubishi Electric discusses the drivers for universities to achieve zero carbon in their built environment – and the challenges.

Calendar
  • Calendar Icon
    11 November, 2020, 10:00 - 12 November, 2020, 16:00
    elemental
  • Calendar Icon
    20 November, 2020, 19:00 - 23:59
    CSA Awards