Mikrofill updates boilers at Telford police station

Mikrofill, space heating, boiler, hot water, DHW

Six Mikrofill 130 kW condensing boilers that can each modulate down to 10% of full load have replaced aging heating plant at Malinsgate Police Station in Telford of West Mercia Police. These stainless-steel boilers were installed with a Mikrovent low-loss header/air and dirt separator, a pre-commissioned Mikrofill pressurisation package and a modular frame kit.

All services were maintained during the 6-week project thanks to the phased design programme by services consultant ESDP and the efforts of mechanical installer Lord Combustion services.

The new equipment serves constant-temperature and variable-temperature systems with a mixture of radiators, fan convectors and air-handling units. There is also a DHW circuit.

For more information on this story, click here: Oct 2015, 133
Related links:
Related articles:



modbs tv logo

Commercial landlords face MEES compliance crunch

Two-thirds of UK commercial real estate (CRE) owners admit they are “not fully compliant” with energy efficiency regulations, according to new research from smart buildings specialist LMG. 

Recognising outstanding achievements at CIBSE Building Performance Awards 2025

The Park Plaza Westminster Bridge in London came alive on 27th February 2025 for the prestigious CIBSE Building Performance Awards.