Mikrofill updates boilers at Telford police station

Mikrofill, space heating, boiler, hot water, DHW

Six Mikrofill 130 kW condensing boilers that can each modulate down to 10% of full load have replaced aging heating plant at Malinsgate Police Station in Telford of West Mercia Police. These stainless-steel boilers were installed with a Mikrovent low-loss header/air and dirt separator, a pre-commissioned Mikrofill pressurisation package and a modular frame kit.

All services were maintained during the 6-week project thanks to the phased design programme by services consultant ESDP and the efforts of mechanical installer Lord Combustion services.

The new equipment serves constant-temperature and variable-temperature systems with a mixture of radiators, fan convectors and air-handling units. There is also a DHW circuit.

For more information on this story, click here: Oct 2015, 133
Related links:
Related articles:



modbs tv logo

Industry urged to see Clean Heat Market Mechanism target as opportunity

The UK government has confirmed that the next phase of the Clean Heat Market Mechanism (CHMM) will set an 8% target for the proportion of heat pumps to fossil fuel boiler sales.

2025 CSA Awards winners announced

The Commissioning Specialists Association (CSA) returned to London on the evening of 2nd October for the staging of its 10th Annual Awards Ceremony.