HDR I Hurley Palmer Flatt completes Building Services for RB plc’s state-of-the-art Science and Innovation Centre

HDR
The GMP Building

 

HDR I Hurley Palmer Flatt completed building services for the the S&I Centre, with brand new consumer health laboratory facilities, consisting of the refurbishment of the existing Kingston Works North, (KWN), office building, as well as creating the new GMP laboratory building and a linking atria, known as the Innovation Pathway. HDR I Hurley Palmer Flatt worked closely with architects Ryder and Scott Brownrigg to create a flexible, energy efficient scheme.

This project is the first milestone of RB’s ongoing £200m investment programme in Hull city. Alongside the new Science & Innovation Centre, RB is committing £95m to significantly upgrade the manufacturing facilities on the Hull site which employs 1,400.

The project incorporates the existing KWN Building and Humber Suite, both historic office buildings dating back to the 1920s, which have been remodelled and seamlessly connected to the building by the imaginative multi-level Innovation Pathway.

The new GMP building accommodates the research laboratories and clean rooms that had previously been residing in the Kingston Works South (KWS building) on an unplanned and evolving basis for the last 35 years.

The building was named The GMP building, and it is designed to accommodate the various user groups: scientists, experts in research and development and product testers. GMP also provides a state-of-the art clean room suite known as the Pilot Plant, where the air purity, temperature humidity and pressure are closely controlled.

The large air plant is located at the end of each wing on all floors of the GMP building, rather than centrally located. This means that any adaption of the floorplate could be achieved without affecting other floors and end-user groups. This has the added advantage of avoiding large vertical ductwork routes.

Another key feature of the approach to the services’ design was to use off-site prefabrication of the large roof plant room, which houses heating and steam boilers, water tanks, pumps, a Reverse Osmosis  water treatment plant, Gen Set and Uninterruptible Power Supply. This meant the construction of the plant room could progress alongside the construction programme and could be delivered to site and craned onto the roof.

The building has been designed to be sustainable and energy efficient, as part of RB’s commitment to continually reduce emissions while growing the business.

Key low energy and sustainable design features include PV cell electrical energy supplies, rain water harvesting, VRF reverse cycle heat pump systems for heating and cooling within KWN and The Humber Suite and the linking Innovation Pathway atria.

Carbon monoxide sensing and air system modulation were also installed within all areas of occupancy fluctuation. LED lighting is featured throughout, with intelligent and addressable lighting controls.

Design features have been benchmarked against the globally recognised LEED (Leadership in Energy and Environmental Design) standard, with the target rating for the S&I Centre being LEED Gold.

The new facility not only sets a new green benchmark for the client, but has also created a vastly improved working environment, ensuring that RB remains at the forefront of consumer health research research.

Related links:



modbs tv logo

First keynote speakers announced by Europump

The first two keynote speakers have been announced for an annual event being hosted by the British Pump Manufacturers Association (BPMA).

‘Landmark’ prosecution of online seller welcomed by REFCOM

The air conditioning and refrigeration industry’s largest safety register REFCOM has welcomed the successful prosecution of online sales company Appliances Direct (AD) for breaching F-Gas Regulations.