Birmingham contractor fits out huge solar farm in double-quick time

JT Hawkes, Solar PV

The design, installation and commissioning of the electricity plant for this £12 million 5 MW solar farm near Swindon was completed in just six weeks by Birmingham electrical-services contractor JT Hawkes — enabling it to go live before Government changes to the Feed-in Tariff took effect on 1 August. Westmill Solar Farm is on a site that also has five wind turbines.

The clients were Blue Energy and Low Carbon Solar. The installation comprises nearly 23 000 solar PV panels from Abakus of Germany.

JT Hawkes designed and installed the entire power-distribution network, including building trenches for 184 km of solar cable and 32 kV power cabling. The brief also involved fitting inverters to convert DC electricity to AC for feeding into the National Grid via two electricity sub-stations.

Related links:
Related articles:



modbs tv logo

Can I use my Air Conditioning system?

If your system hasn't been used in months it's an important question. 

New air-cooling system from Weiss Technik has unique four-stage safety concept and innovative thermal disinfection

The Coronavirus outbreak has increased awareness of hygienic room climate issues, ventilation and air-conditioning systems in public buildings. If planned poorly or not serviced properly, air conditioning units can quickly turn into transmitters of disease-causing germs.

Calendar
  • Calendar Icon
    11 November, 2020, 10:00 - 12 November, 2020, 16:00
    elemental
  • Calendar Icon
    20 November, 2020, 19:00 - 23:59
    CSA Awards