Voltage optimiser cuts electricity bills by 17.3%

An immediate 17.3% reduction in electricity consumption has been achieved following the installation of a voltage optimiser at Peasley Cross Hospital in St Helens. Before the installation of the equipment from Streamline Power, the average voltage on site was 246.3 V, peaking at 252.8 V —close to the legal maximum of 253 V. The voltage optimiser has reduced the voltage to 223 V, balanced the incoming phases and controlled the incoming voltage to within 0.5% of target.

The project will pay for itself in 32 months and deliver an internal rate of return of 39%.

Installation took two working days, and the electricity supply was switched over during a period of low demand in the working day.

For more information on this story, click here: December 2011, 81
Related links:
Related articles:



modbs tv logo

Four new appointments at BCIA

THE Building Controls Industry Association (BCIA) has appointed a new Vice-President and three new additions to its Management Committee.

Engineering services alliance welcomes retentions reporting legislation

Engineering services alliance Actuate UK has warmly welcomed the new secondary legislation which will require reporting of cash retentions held by the large construction companies under the Reporting Regulations.