NG Bailey has been appointed principal contractor by North Tees & Hartlepool Foundation Trust to construct a new energy centre at the University Hospital of North Tees. This £14 million project will be on the existing hospital estate and house a new primary intake substation.

It will have N+1 emergency generators, CHP, boiler plant and associated 30 m-high stacks, oil-fuel storage and distribution, water storage and associated M&E infrastructure.

The NG Bailey team developed a detailed methodology showing how the complex critical services will be maintained during the build phase, as well as the commissioning and switchover protocol to transfer from the aging infrastructure to the new substations.

As part of its principal-contractor role, NG Bailey will also be responsible for delivering building works, including the superstructure and forming of the major energy centre building complex. Two reinforced-concrete below-ground walkways will be created to link the energy centre to the existing hospital infrastructure.

The new energy centre will be more reliable, more energy efficient and more environmentally friendly. It will be operational in 2018.

Related links:
Related articles:



modbs tv logo

Industry urged to see Clean Heat Market Mechanism target as opportunity

The UK government has confirmed that the next phase of the Clean Heat Market Mechanism (CHMM) will set an 8% target for the proportion of heat pumps to fossil fuel boiler sales.

2025 CSA Awards winners announced

The Commissioning Specialists Association (CSA) returned to London on the evening of 2nd October for the staging of its 10th Annual Awards Ceremony.