Hospital refurbishment reclaims exhaust heat

Thermal Technology, heat recovery, AHUs
This Thermal Technologies AHU serving a London hospital can transfer 500 kW of heat from exhaust air to supply air — and there are four of them.

Over 2 MW of heat can be recovered from exhaust air by four large air-handling units installed as part of ongoing refurbishment work at the Royal Free Hospital in London. Each of the four roof-mounted units supplied by thermal Technology can handle 27 m3/s and recover 501 kW of heat using an exhaust-air run-around coil.

The heat is supplied to matching coils in the refurbished ground-floor supply units.

Each AHU is about 6 m long, 4.7 m wide and 2.5 m high. To simplify lifting and transportation, each unit was supplied split into two equal sections for on-site assembly.

To protect the run-around coils from airborne dust, G4 bag filters were fitted. They have a far greater dust-holding capacity than panel filters, extending service intervals between filter changes.

For more information on this story, click here: May10, 125
Related links:
Related articles:



modbs tv logo

Yorkshire and Humber leaders set out plans to tackle skills shortages

Leaders from across Yorkshire and the Humber came together on Friday 11th September to launch ambitious plans aimed at tackling the region’s growing construction skills shortages.

Six in 10 UK businesses look to adapt operations in response to extreme heat

According to the Q2 Barclays Business Prosperity Index, six in 10 businesses surveyed (60%) have either increased investment to adapt to extreme heat (37%) or are considering doing so (23%).