Hulley & Kirkwood consulting engineers has provided the mechanical and electrical services for the new £112 million Hartswood South unit of Thameside Hospital The project included a standalone energy centre to serve this building and the Etherow building.

The energy centre accommodates the 2.4 MW district-heating plant, including a 500 kW biomass boiler to meet about 18% of the heating requirement. The services also include specialist medical gases.

Related links:
Related articles:



modbs tv logo

Built environment professionals remain positive on future of Net Zero

A recent survey by global climate tech firm IES has revealed that nearly three-quarters of UK built environment professionals believe achieving a Net Zero built environment by 2050 is within reach.

BESA research suggests clients are yet to engage with new building safety regime

Construction clients are failing to engage with the new building safety regime, according to research carried out by the Building Engineering Services Association (BESA).